AAEM LLC completed delivery of diesel-generator sets for LNPP-2

AAEM LLC completed delivery of diesel-generator sets for LNPP-2 14.09.2017

AAEM LLC completed delivery of diesel-generator sets for LNPP-2

LNPP-2 held successful extensive testing of the auxiliary power supply systems under complete blackout conditions.

With the loss of auxiliary power, the automatic reactor protection responded in accordance with the design, all four emergency power supply diesel-generator sets delivered by AAEM LLC started automatically and secured stepwise connection of the safety systems of the power unit. No failures of the electrical equipment in switching from the operating power supplies to the emergency ones were recorded. Also, no failures of the process equipment in switching from the emergency power supplies to the operating ones were recorded.

The unit is equipped with five such sets - four providing emergency power supply and one for BoP, each rated at 6.3 MW. Their performance meets the most stringent requirements for reliability, availability, speed of response and is instrumental in safe operation of the nuclear power plant.

AAEM LLC, together with other Atomenergomash companies, is responsible for the entire scope of works, including design, production control, quality assurance, delivery of the DGS, and provides field servicing and commissioning.